Following on from a recent incident in the East Midlands area using Enerpac Stressing Kits, I am advising members to invoke the Work Safe Procedure should they be asked to use this kit prior to any subsequent investigation

 

The investigation will make recommendations on the safest method of working whilst stressing/destressing, and which equipment is deemed fit for purpose. 

 

Concerns have also been raised in others areas regarding the Enerpac Stressing Kit not being fit for purpose.  

 